|
|
Stormwater
Tolman
Engineering has extensive experience with feasibility assessments,
planning, design, permitting, construction and construction
oversight of stormwater management systems. As part of our
municipal engineering practice we have designed various drainage
projects from very small to vary large. We have successfully
completed drainage and other engineering projects for over a decade
for a number of clients which exemplifies our competence and client
driven focus. We have the experience, technical expertise,
commitment to excellence and resources to provide outstanding and
timely service. Provide below is a brief summary for a number
of stormwater projects completed by Tolman Engineering staff.
Village of Fredonia – University
Drainage Project
Evaluation of S.U.N.Y. College at Fredonia’s existing storm drainage
system capacity with EPA SWMM. Evaluation of the feasibility
of connecting a proposed drainage system to SUNY Fredonia’s existing
drainage system. Detailed investigation of the hydrologic and
hydraulic components of the existing and proposed drainage systems.
Checked existing, proposed, and future SWMM stormwater model with
Pondpack to verify results. Creation of a report for review
and approval of the proposed drainage project by SUNY Fredonia and
NYS Dept. of State. Developed design drawings and contract documents
for public bidding to contractors. Completed construction
contract administration including change orders, pay applications,
submittal review, etc. Provided construction oversight and
supervision of contractor during construction. Provide
construction oversight and assistance to Village of Fredonia’s
forces during construction.
Facilities designed included approximately 700 linear feet of 42”
CPP storm main, 520 linear feet of 30” CPP storm main, 3,000 linear
feet of 24” CPP storm main, 2,220 linear feet of 18” CPP storm main,
and 1,040 linear feet of 12” CPP storm main. The total construction
project is estimated to be over $1.2 million. A portion of the
project was constructed by a private contractor and a portion was
completed by Village of Fredonia’s forces.
Cummins Jamestown Engine Plant Site Improvements
Designed trailer parking area, parking lot expansion, new truck
road, and stormwater management (drainage) facilities. Design
included a wet pond, micro-pool extended detention pond, new closed
drainage system, and open channels. Performed hydrologic and
hydraulic analysis of existing site drainage system including
modeling existing detention ponds. Performed stormwater
modeling for post construction stormwater management, including
removal of existing ponds. Worked with subconsultant to perform
wetland delineation and obtain Army Corps of Eng. jurisdictional
determination. Evaluated potential alternatives and refined
selected design to minimized wetland disturbance. Worked with
subconsultant to develop Wetland Mitigation Plan and obtain Army
Corps of Engineers Wetland Permit. Completed a Stormwater
Pollution Prevention Plan and obtained NYSDEC SPDES Permit for
Stormwater Discharge. Created construction drawings and
details for use by Cummins in obtaining bids from private
contractors. Provided construction oversight and addressed
contractors and owners questions during construction. Provided
weekly erosion and sediment control inspections and generated
inspection reports for site log book.
Facilities designed included 272,000 gallon wet pond, 1.4 million
gallon micro-pool extended detention pond, 120 linear feet of 48”
CPP storm main, 380 linear feet of 42” CPP storm main, 270 linear
feet of 30” storm main, 900 linear feet of 24” CPP storm main, 625
linear feet of 15” CPP storm main, 540 linear feet of 12” CPP storm
main, 80 linear feet of 36” diameter road culvert, and approximately
880 linear feet of open channel. The total cost of the project is
estimated to be over $2 million. Construction contract
administration was completed by Cummins, therefore actual cost is
unknown.
Village of Lakewood – Chautauqua Avenue Reconstruction
Road reconstruction including relocating utilities, installation of
a clock tower, retaining walls, traffic light and signage.
Designed new road, driveway entrances, sidewalks, parking areas,
utilities, retaining walls, clock tower, and traffic light.
New utilities included underground electric, water main, bore under
railroad tracks, and a closed drainage system. Coordinated
underground relocation of existing utilities with utility companies.
Worked with Architect and community to develop historic streetscape
plan including a landscape plan. Created cost estimates that
were used to determine the funding needed to complete the project.
Completed an Engineering Report and obtained Department of Health
Approval for the proposed water main. Developed contract
documents (drawings and specifications) for public bidding to
private contractors. Completed construction contract
administration including change orders, pay applications, submittal
review, etc. Provided construction oversight and supervision
of contractor during construction.
Facilities designed included approximately 2,800 linear feet of road
reconstruction, 2,337 linear feet of closed drainage system, 2,830
linear feet of 8-inch water main, 100 linear feet of cased road
bore, 12,370 linear feet of underground electrical conduit, and
5,600 linear feet of underdrain. The total cost of the project
was approximately $2.3 million
Warren County Chamber of Business & Industry – Brokenstraw
Industrial Park
Designed a green field industrial park with an access drive,
utilities, and stormwater management facilities (ready for
development). Coordinated a wetland delineation and
jurisdiction determination (only PADEP regulated the project area
wetland). Met with PA Department of Environmental Protection
who establish wetland detention policy based on project.
Completed Pennsylvania Natural Diversity Inventory (PNDI) Project
Environmental Review. Coordinated geotechnical investigation
to classify on-site soils and infiltration rates. Designed
access drive and maximum impervious area for industrial lot
development. Designed drainage system including an
infiltration basin and vegetated drainage swales. Completed an
Erosion and Sediment Control Plan and a Post Construction Stormwater
Management Plan. Obtained a National Pollutant Discharge
Elimination System (NPDES) General Permit. Obtained a
Pennsylvania Department of Transportation Highway Occupancy Permit.
Obtained a PA Department of Environmental Protection Minor Road
Crossing (GP-7) General Permit. Developed design drawings,
details, technical specifications, and probable cost estimate.
Facilities designed on the 32 acre project site included
approximately 500 linear feet of access drive, 1,060 linear feet of
vegetative drainage swales, 340 linear feet of storm main, and a
1.03 million gallon infiltration basin. The total cost is
approximately $450,000.
R.W. Larson Architects – Community Eye Care Building & US Forest
Service Office Building
Provided site design for new Community Eye Care building and new US
Forest Service Office building in two phases. Designed
grading, pavement, sewerage system, drainage system and infiltration
and detention (stormwater) basin. The stormwater basin
provides water quality treatment, provides groundwater recharge, and
controls peak runoff rates. Designed permanent erosion and
sediment control measures on steep cut slope and pond inlets.
Created Post Construction Stormwater Management Plan and Erosion and
Sediment Control Plan to PADEP requirements. Coordinated
geotechnical investigation to determine on-site soil types and
infiltration rates. Completed Pennsylvania Natural Diversity
Inventory (PNDI) Project Environmental Review. Obtained a
National Pollutant Discharge Elimination System (NPDES) General
Permit. Obtained Pennsylvania Department of Transportation
Driveway Permit. Obtained approval of Conewango Township (i.e.
design conformed to Township’s Stormwater Management Ordinance).
Performed hydrologic and hydraulic modeling of proposed drainage
system to ensure adequate flow capacity. Created construction
drawings and details for use in obtaining bids from private
contractors.
Facilities designed on the 6.3 acre project site included 429,000
gallon infiltration/detention basin, approximately 1,320 linear feet
of storm main ranging in size from 18-inch to 12-inch in diameter,
and approximately 510 linear feet of grass drainage swale. The
work was completed as a subconsultant to an Architect, as such the
actual construction cost is not known (most likely over $6 million
dollars).
Special Metals Corporation – Site Stormwater Improvements
Performed on-site investigation of underground drainage system
including coordination of video inspection. Developed Stormwater
Pollution Prevention Plan for a project classified as
“redevelopment”. Designed stormwater drainage system
including a Vortechs Model 2000 Stormwater Treatment System.
Obtained NYSDEC SPDES Permit for Stormwater Discharge from
Construction Activity. Completed presentation to NYSDEC, City
of Dunkirk, Chautauqua County, and adjacent property owners.
Completed preliminary cost estimates of alternative designs for
stormwater project selection by owner. Designed two
underground stormwater pumping stations and associated stormwater
forcemain. Performed hydrologic and hydraulic stormwater
modeling of the existing and proposed drainage systems.
Developed a Stormwater Engineering Report that was submitted to and
approved by the City of Dunkirk. Obtained R.O.W. Occupancy
Permit from Chautauqua County Department of Public Facilities.
Developed contract documents for bidding to private contractors and
reviewed construction submittals. Provided weekly erosion and
sediment control inspection and construction duration inspection.
Facilities designed on the 8.3 acre project site included
approximately 1,450 linear feet of gravity storm main, 700 linear
feet of stormwater forcemain, 5,540 GPM stormwater pump station, and
2,080 GPM stormwater pump station. The total cost is
approximately $500,000.
Flynn Battaglia Architects – SUNY Fredonia Community Daycare
Designed site grading, parking area, access drive, sidewalk,
sanitary sewer, and stormwater management (drainage) facilities.
Performed stormwater modeling for existing conditions and proposed
conditions stormwater runoff. Coordinated geotechnical
investigation to classify soil types and determine on-site
infiltration rates. Designed underground infiltration system
including pre-treatment system to ensure long-term performance of
infiltration. Pre-treatment consists of an isolator filter
row, floatables trap, deep sumps, vegetative swale, and vegetative
filter strip. Worked with Architect to obtain Leadership in
Energy and Environmental Design (LEED) Certification for project.
Reviewed project area for registered state or national historic
places and any potential impact by project. Completed a
Stormwater Pollution Prevention Plan and obtained NYSDEC SPDES
Permit for Stormwater Discharge. Created construction
drawings, details, and technical specifications for use in obtaining
bids from private contractors. Designed was reviewed and
approved by State University of New York, College at Fredonia.
Performed drafting services for the completion of a landscape plan
drawing designed by a Landscape Architect. Provided
construction oversight, weekly erosion and sediment control
inspections, and submittal review.
Approximately 14,000 SQFT building, 3.5 acre project site, 39,000
gallon underground infiltration system, 1,480 linear feet of storm
main, and 365 linear feet of drainage swale. The total cost of
the daycare project is $4.0 million
Town
of Busti – Huntington Wood/Shadow Creek Subdivisions
Provided stormwater management design for Huntington Woods and
Shadow Creek subdivision. Created a map, plan, and report for
the establishment of a drainage district for the project.
Performed field investigation to verify drainage patterns and
watershed areas. Performed stormwater modeling of the existing
and proposed drainage system to comply with permit requirements.
Designed two off-line micro-pool extended detention ponds that work
together to control peak stormwater runoff. Designed relocated
stream channel and obtained Nationwide Permit from Army Corps of
Engineers. Designed temporary diversion ditch and permanent
cutoff ditch for phased construction. Created a Stormwater
Pollution Prevention Plan and obtained a SPDES General Permit from
NYSDEC. Designed stormwater plan and erosion and sediment
control plan to account for four phased construction. Created
construction drawings, details, and technical specifications for use
by developers contractor during construction. Complete weekly
erosion and sediment control inspections and generated required
reports during construction of ponds.
Drainage area = 148 acres, total project site = 51 acres, Pond 1 =
252, 000 gallons, Pond 2 = 1,033,000 gallons, approximately 250
linear feet of relocated stream channel, approximately 400 linear
feet of temporary diversion ditch, and approximately 1,661 linear
feet of cutoff ditches. The cost of the stormwater management
facilities are estimated at $250,000.
Town of Hanover – Rider Road Culvert Replacement
Performed a hydrologic analysis of the watershed using PondPack, a
stormwater modeling software package. Performed hydraulic
analysis using the procedures in the Federal Hydraulic Design of
Highway Culverts manual. Evaluated potential alternative
designs based on FEMA and SEMO requirements for funding.
Created engineering report for review and approval of culvert
replacement project by FEMA and SEMO. Completed a preliminary
construction cost estimate to receive project funds from FEMA and
SEMO. Designed replacement culvert based on no increase to the
100-year flood water elevation. Designed erosion and sediment
control measures, access drive, retaining walls, and road closure
plan. Obtained permits from the U.S. Army Corps of Engineers
and the NYS Department of Environmental Conservation.
Developed contract documents (drawings and specifications) for
public bidding to contractors. Completed construction contract
administration including change orders, pay applications, submittal
review, etc. Insured compliance with FEMA and SEMO contract
requirements during construction. Provided construction
oversight and supervision of contractor during construction.
Facilities designed included 168 linear feet of 84” diameter
reinforced concrete pipe with approximately 25-feet of soil cover.
Watershed (drainage) area is approximately 341 acres. The
total cost of the project was approximately $450,000.00.
United Refinery Company – Truck Stacking and Site Improvements
Redeveloped existing residential and commercial property to provide
new office space and truck staging area. Designed layout for
new truck staging area, parking areas, access drives, driveways, and
drainage system. Designed an underground oil/water separator
and an up-stream stormwater by-pass chamber. Performed
hydrologic and hydraulic modeling of proposed drainage system to
select pipe size for 25-Yr 24-Hr storm. Perform on-site
investigation to obtain existing information vital to the proper
design of the project. Created an Erosion and Sediment Control
Plan to comply with the PA Erosion and Sediment Pollution Control
Manual. Obtained Pennsylvania Department of Transportation
Highway Occupancy Permit. Obtained approval from the City of
Warren to replace existing catch basin and remove existing parking
area on street. Created construction drawings and details for
use by United Refining in obtaining bids from private contractors.
Facilities designed on the 4.7 acre project site included 3,000 GPM
oil/water separator, approximately 430 linear feet of 30-inch CPP
storm main, 400 linear feet of 24-inch storm main, 193 linear feet
of 18-inch storm main, 216 linear feet of 15-inch storm main, and
926 linear feet of 12-inch storm main. The total construction
cost of the project is approximately $2.1 million. |
 |
 |